Bexhill to Hastings link road could open sooner if conditions are varied

The new Bexhill to Hastings link road could open sooner if minor amendments to the plans are agreed next week.
4/12/14- Update pics of the Bexhill to Hastings Link Road (BHLR)- bridge construction near Upper wilting Farm. SUS-150723-1156160014/12/14- Update pics of the Bexhill to Hastings Link Road (BHLR)- bridge construction near Upper wilting Farm. SUS-150723-115616001
4/12/14- Update pics of the Bexhill to Hastings Link Road (BHLR)- bridge construction near Upper wilting Farm. SUS-150723-115616001

East Sussex County Council was set to open the new route in May, but work on the £116m project was delayed due to a wet winter, and the authority has since been tight-lipped on any revised opening date.

Previously it has said it will be open by this autumn, while the one-off Bexhill to Hastings Link Road 10k race has been set for September 20.

Hide Ad
Hide Ad

Now the authority’s planning committee will decide at a meeting this Wednesday whether to allow the public to use the road before landscaping works are completed.

Picture of Bexhil to Hastings link road works in December 2014 bridge construction near Upper wilting Farm. SUS-140412-130008001Picture of Bexhil to Hastings link road works in December 2014 bridge construction near Upper wilting Farm. SUS-140412-130008001
Picture of Bexhil to Hastings link road works in December 2014 bridge construction near Upper wilting Farm. SUS-140412-130008001

Under the terms of the approved planning permission the entire link road cannot be opened without the landscaping works and the ‘greenway’, which is being designed for cyclists, pedestrians and horse riders, being completed.

The county council has not received any objections, but Cllr Michael Ensor has said while he understands the reason behind the amendment, he would like assurances that all the landscaping and environmental works for the southern section from the A259 as far as the Ninfield Road bridge are fully completed before the road is opened.

This is after residents complained environmental works for this section were not completed before the diversion route was opened.

Hide Ad
Hide Ad

The officers’ report said the changes would allow a degree of flexibility to open the road ‘should the need arise’, but permission would still be needed from the director for planning and environment.

Don’t miss out on all the latest breaking news where you live.

Here are four ways you can be sure you’ll be amongst the first to know what’s going on.

1) Make our website your homepage

2) Like our Facebook page

3) Follow us on Twitter

4) Register with us by clicking on ‘sign in’ (top right corner). You can then receive our daily newsletter AND add your point of view to stories that you read here.

And do share with your family and friends - so they don’t miss out!

Always the first with your local news.

Be part of it.